Commercial Standby Generators
Commercial standby generator installation & service for Bergen County businesses — transfer switches, integration, testing. Call (201) 391-7759.
Pascale Electric, Inc. — 130 Kinderkamack Road, Park Ridge, NJ 07656.
Call (201) 391-7759
or email info@pascaleelectric.com.
The short answer
A commercial standby generator with an automatic transfer switch keeps a business running when utility power fails, and the decision that shapes the entire project is not the size — it is the classification. NEC Article 700 covers legally required emergency systems for life safety and must restore power within 10 seconds; Article 701 covers legally required standby at up to 60 seconds; Article 702 covers optional standby chosen by the owner to protect against business loss, with no code-mandated transfer time. That classification drives the transfer switch, the wiring separation, the fuel arrangement, the commissioning and the ongoing testing obligations.
Commercial Generators — key facts
- Classification first
- NEC 700, 701 and 702 impose different transfer times, wiring-independence rules and maintenance obligations. Establishing which one applies to your building is step one, not a detail.
- Multi-trade project
- A commercial generator involves the electrical contractor plus a concrete pad, a licensed gas fitter or fuel contractor, sometimes structural engineering and crane or rigging for larger units.
- Lead times
- Generator sets, automatic transfer switches and the associated distribution gear carry the longest lead times on the project and are ordered as soon as the scope is locked.
- Testing and records
- Emergency systems must be tested periodically on a schedule acceptable to the authority having jurisdiction, and a written record of tests and maintenance must be kept.
- Work sequencing
- The tie-in requires a planned outage. On most commercial buildings that happens after hours or on a weekend, with the duration agreed in advance.
You need this if
- An outage costs you real money by the hour — refrigeration, process equipment, a data room, a medical practice with scheduled patients, or a retail floor that simply cannot transact in the dark.
- Your building code or the authority having jurisdiction requires emergency or legally required standby power for egress lighting, exit signs, fire alarm, smoke control or an elevator.
- You are on a wooded, storm-exposed Pascack Valley circuit and have lost power more than once in the last few winters.
- You have a portable generator arrangement with cords and manual switching that is neither safe nor code-compliant, and you know it.
- Your existing generator is aging, has failed a test, will not accept load, or has no maintenance record at all.
- A tenant lease, franchise agreement, insurer or regulator requires documented standby power.
Commercial Generators
Downtime costs money — and for some businesses, safety. Standby power is the piece of the commercial side of the shop that gets judged during a blackout. We install and service commercial standby generators and transfer switches sized to keep your critical systems (or your whole operation) running.
What we do
Generator and automatic transfer-switch installation, electrical integration, load configuration, and ongoing testing and service.
How the job runs
- Determine the classification and the load
- We work with you, and with your design professional or the authority having jurisdiction where required, to establish whether the system falls under Article 700, 701 or 702, and to define what actually has to run. That decision drives every other choice on the project — and it is where a system gets undersized or, just as commonly, over-scoped.
- Site evaluation and trade coordination
- We look at where the unit can physically go with the required clearances, how far it is from the service and the transfer switch, where the fuel comes from, whether the pad location is accessible for delivery and future service, and what the exhaust and ventilation require. Then we identify which other trades the project needs.
- Design, permits and drawings
- Electrical permit, plus the building and plumbing permits the associated work requires. Larger units typically need engineering calculations and drawings for structural review of the pad. We coordinate the submissions so the permits move together rather than in sequence.
- Procurement and site preparation
- Generator, transfer switch and gear are released early. While they are in production, site work proceeds: pad, conduit, feeders, and the gas or fuel supply run by the licensed gas fitter or fuel contractor. Gas service upsizing in particular needs to be complete before the unit arrives.
- Set, connect and tie in
- The unit is set and, on larger installations, rigged into place. We land the feeders, install and wire the transfer switch, reconfigure the distribution so the standby loads are on the right side of the switch, and perform the utility tie-in during the agreed planned outage.
- Commission, train and document
- Acceptance testing with a live transfer under load, verification of transfer and retransfer timing, exercise-schedule programming, and a walkthrough with your staff so someone on site knows what the annunciator is telling them. You get the closed permit, the commissioning results and a starting maintenance and testing record.
What's included
- Classification review and standby load definition, coordinated with your design professional or the authority having jurisdiction where required
- Site evaluation covering clearances, service access, fuel routing, exhaust and future serviceability
- Electrical permit filing and coordination of the associated building and plumbing permits
- Feeders, conduit, distribution reconfiguration and automatic transfer switch installation and wiring
- Setting and electrical connection of the generator, and the utility tie-in during a planned outage
- Acceptance testing with live transfer, transfer-timing verification and exercise-schedule programming
- Staff walkthrough covering the annunciator, the exercise schedule and what to do when it runs
- Closeout documentation and the start of the written test and maintenance record
- Ongoing scheduled testing and service to keep the record current
What's not included
- Gas piping, gas service upsizing and fuel-tank installation — performed by a licensed plumber, gas fitter or fuel contractor and coordinated by us
- Concrete pad or foundation construction, and the structural engineering and drawings larger units require for review
- Crane and rigging services for large units, and any street or lot closure permits that come with them
- Sound-attenuation enclosures beyond the manufacturer's standard offering, and acoustic barrier construction
- Roofing, structural reinforcement and vibration isolation design for elevated or rooftop installations
- Utility charges for gas or electric service modifications, and any utility interconnection review for closed-transition transfer
- Fuel supply, fuel polishing services and fuel-quality management for diesel installations
What affects the cost
- System classification
- An Article 702 optional standby system is the least prescriptive. Articles 700 and 701 add mandated transfer times, wiring independence from general building wiring, selective coordination and commissioning obligations — all of which change the gear and the labor.
- How much of the building you back up
- Backing up defined critical loads means a smaller unit and a smaller transfer switch but more work reconfiguring the distribution to separate those loads. Backing up the whole service means a larger unit but simpler switching.
- Distance from the unit to the service
- Feeder length, conduit routing, and whether the run is underground, through the building or across a roof drive both material and labor, and can rival the electrical cost of the unit itself on a long run.
- Fuel source and supply work
- Natural gas avoids on-site storage but frequently requires the gas service to be upsized before the unit arrives. Diesel avoids utility dependence but brings tank, containment and fuel-management scope.
- Transfer switch type
- Open transition is the baseline. Delayed transition protects large motor loads. Closed transition eliminates the interruption but requires utility coordination and approval. Bypass-isolation lets the switch be serviced without dropping the load, and costs accordingly.
- Site access and placement
- A unit that can be delivered and set at grade near the service is the straightforward case. Rooftop, courtyard, below-grade or tight urban placements bring rigging, structural work and access planning.
- Permits, structural review and commissioning
- Multi-trade permitting, structural review of the pad, and formal acceptance testing are real calendar and cost items on a commercial generator that do not exist on a small residential install.
NEC 700 vs. 701 vs. 702 — which system are you building
- What it protects — Article 700 — Emergency: People getting out — egress illumination, exit signs, fire alarm, some elevators — Article 701 — Legally Required Standby: Responders and hazard mitigation — smoke control, sewage, communications, some process — Article 702 — Optional Standby: Your business — refrigeration, data, process, continuity of operations
- Who requires it — Article 700 — Emergency: Required by law or the authority having jurisdiction — Article 701 — Legally Required Standby: Required by a governmental agency for public safety — Article 702 — Optional Standby: The owner's decision
- Transfer time — Article 700 — Emergency: Not to exceed 10 seconds — Article 701 — Legally Required Standby: Not to exceed 60 seconds — Article 702 — Optional Standby: No code-mandated time; automatic or manual
- Wiring independence — Article 700 — Emergency: Required — kept independent of general building wiring — Article 701 — Legally Required Standby: Required — Article 702 — Optional Standby: May share raceways, boxes and cabinets with general wiring
- Testing obligation — Article 700 — Emergency: Periodic testing on an approved schedule, with written records — Article 701 — Legally Required Standby: Periodic testing on an approved schedule, with written records — Article 702 — Optional Standby: Not subject to the same code testing mandate
- Typical Bergen County example — Article 700 — Emergency: An assembly, healthcare or larger occupancy with code-required egress power — Article 701 — Legally Required Standby: A facility where an agency mandates standby for public safety — Article 702 — Optional Standby: A restaurant protecting walk-ins, or an office protecting a server room
Permits and code
- NEC Article 700 emergency systems must have power available within the time required for the application and not exceeding 10 seconds. Article 701 legally required standby allows up to 60 seconds. Article 702 optional standby has no code-mandated transfer time and may be automatic or manual.
- Articles 700 and 701 require wiring to be kept independent of general building wiring, and both impose maintenance and testing obligations. Article 702 wiring may occupy the same raceways, boxes and cabinets as other general wiring, and 702 systems are not subject to that testing mandate.
- NEC 700.3 requires the authority having jurisdiction to conduct or witness a test on installation and periodically thereafter, testing on a schedule acceptable to that authority, and a written record of tests and maintenance.
- NFPA 110 classifies emergency power supply systems by Level — Level 1 where failure could result in loss of human life or serious injury — and further describes them by Type, the maximum time the load may be without power, and Class, the minimum time the system must run at full load without refueling. On-site fuel is sized to the assigned Class and may not be shared with another purpose.
- Whether a natural-gas-only supply is acceptable for a given system depends on the classification and the authority having jurisdiction's assessment of off-site supply reliability. For Level 1 systems in locations with a high probability of interruption, on-site fuel storage adequate for the Class duration is expected. A commercial generator is also a multi-permit project: the gas or fuel work is performed under the appropriate trade license, and the pad is inspected against the approved structural drawings where review is required.
In Bergen County & the Pascack Valley
The Pascack Valley loses power the way wooded, mature-tree suburbs do — not constantly, but hard and for long stretches when a nor'easter or a wet snow comes through. That plays out differently depending on the meter. Businesses in Montvale, Allendale, Ramsey, Franklin Lakes and Upper Saddle River are on Rockland Electric (Orange & Rockland). Woodcliff Lake, Hillsdale, Westwood, Emerson and Washington Township are PSE&G. Park Ridge is served by its own borough-owned Electric Department, which means outage restoration, service coordination and any tie-in work go through the municipal utility rather than a large investor-owned one. River Vale and Saddle River are split. The businesses that feel it most are the ones we see calling: restaurants along Westwood Avenue and Kinderkamack Road with walk-ins full of inventory, medical and dental suites with scheduled patients and refrigerated product, the retail and service tenants on the Route 17 corridor whose registers and networks go down with the lights, and the office and corporate properties in Montvale and around Tice's Corner where a dark building means a lost day. Being based in Park Ridge means we are also the ones who show up when the generator that has not been exercised in two years finally gets asked to run.
Commercial Generators FAQs
- Can you back up only critical equipment?
- Yes — we can size a system to cover critical loads or the full facility, depending on your needs and budget.
- Do we need to back up the whole building?
- Not usually, and it is worth resisting the instinct to. Most commercial buildings are better served by identifying the loads that genuinely cannot go down — refrigeration, process equipment, the server room, egress and emergency lighting, security, point of sale — and sizing the system around those. That means a smaller unit and a smaller transfer switch, at the cost of more work reconfiguring the distribution so those loads sit on the standby side. We price both approaches so you can see the tradeoff rather than defaulting to the largest unit.
- Natural gas or diesel?
- Natural gas avoids on-site fuel storage, tank permitting, containment and fuel degradation, and it runs indefinitely as long as the gas supply holds — but it depends on utility supply continuity, and the gas service frequently has to be upsized before the unit arrives. Diesel guarantees fuel on site, which matters where the system's classification requires a defined run duration without refueling, but brings tank containment and fuel-quality management. The classification of your system and the authority having jurisdiction's view of supply reliability often settle the question for you.
- What does an automatic transfer switch actually do, and are there different kinds?
- It senses the loss of utility power, signals the generator to start, and transfers the load once the generator is stable — then transfers back and shuts the unit down when utility power returns. Open transition is the standard, with a brief interruption during transfer. Delayed transition adds a pause in the neutral position so large motor loads spin down first, which matters for elevators and chillers. Closed transition briefly parallels both sources so the load never sees an interruption, and requires utility coordination. Bypass-isolation lets the switch itself be serviced without dropping the load.
- How often does a commercial generator have to be tested?
- It depends on the system's classification and the authority having jurisdiction's approved schedule, but the widely applied practice under NFPA 110 is a weekly inspection and a monthly exercise of about 30 minutes under meaningful load. Diesel systems that do not achieve that monthly loading are subject to a supplemental annual load bank test. Level 1 systems carry a longer comprehensive test at extended intervals. The part that is not optional for emergency systems: a written record of tests and maintenance has to exist and be available.
- How long is the outage when you tie the generator in?
- The tie-in itself is a planned outage, and its length depends on how the distribution has to be reconfigured. A whole-service transfer switch installed ahead of the main distribution is generally a shorter, better-defined window than separating individual critical loads onto a standby panel. We define the window before we schedule it, do it after hours or on a weekend for most commercial buildings, and where the business truly cannot go dark at all we plan a temporary feed. You get the duration in writing, not an estimate on the day.
- We inherited a generator with the building. Where do we start?
- With an inspection and a load test, not with a decision. We check whether it starts and accepts load, verify the transfer switch operates and retransfers correctly, look at the battery, the coolant and block heater, the fuel condition, and whether the exercise schedule is even set. Then we look at whether what it feeds still matches what the building actually needs, since that often drifted over the years. That gives you an honest answer on service versus replace, and it establishes the written test record you should have been keeping.
Towns we serve
- Electrician in Park Ridge, NJ
- Electrician in Woodcliff Lake, NJ
- Electrician in Montvale, NJ
- Electrician in Hillsdale, NJ
- Electrician in River Vale, NJ
- Electrician in Westwood, NJ
- Electrician in Washington Township, NJ
- Electrician in Emerson, NJ
- Electrician in Oradell, NJ
- Electrician in Upper Saddle River, NJ
- Electrician in Saddle River, NJ
- Electrician in Franklin Lakes, NJ
- Electrician in Wyckoff, NJ
- Electrician in Allendale, NJ
- Electrician in Ramsey, NJ